Finalizing stage in Ramada Frankton
We are in the finalising stage of the installation. The scaffoldings are removed from north elevator side opening up main entrance curtain wall. It is a real pressure to see...

Show-room in The International
The first apartment for the show-room in The International project was completed. We are very proud to contribute to that, being responsible for the supply and installation of the massive...

The updates from Ramada Manukau
Manukau site is also making substantial progress. We have the ongoing installations on level 6. The building is rising adding a lot to the touristic potential of South Auckland.

The launch of facade installation in Ramada Frankton
Our team has already launched facade installation processes in Ramada Frankton (Queenstown). The ground and 1st floor punched opening frames are all installed, we are starting to glaze the ground...

Ramada Victoria's progress
Our team on Victoria site has almost completed the installation of the panels on Level 7. We are finishing with balustrades on level 4 and balconies on level 3. The...

Testing of EXO nodes
Our EXO steel nodes successfully passed the testing with the gradual load of up to very high level. A load of 100KN each way was achieved in comparison to project...

Water testing in Ramada Manukau
Our team has done a tremendous job! We have successfully passed the Preliminary water test (AAMA 501.2) on curtain wall system at our Manukau site.
EXO frames for The International are under production
The aluminium frame (400x200x10mm rectangular box in 11.2mts at the longest length) are extruded by the world largest extrusion press for 11000 tones.